2016

FUEL & ASH HANDLING SYSTEM PRAKASA, SAMUTPRAKARN
(APCON POWER PLANT, 2016)
Material: TRASH & WASTE (RDF)
System: SCREW &SUBMEGED CHAIN CONVEYOR
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION
FUEL & ASH HANDLING SYSTEM TEPHA, SONGKHLA
(BIOMASS POWER PLANT, 2016)
Material: PARAWOOD CHIP
System: BELT,CHAIN, SCREW &SUBMEGED CHAIN CONVEYOR
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION
FUEL HANDLING SYSTEM SRABURI, THAILAND
(ETC ENGINEERING, 2016)
Capacity: 5 Tons/Hour
System: BELT,CHAIN,ROLLER BELT CONVEYOR
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION
ASH HANDLING SYSTEM SRABURI, THAILAND
(ETC ENGINEERING, 2016)
Capacity: 0.5-7 CBM/Hr/direction
System: SCREW, SUBMERGED, CHAIN CONVEYOR
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION

2010-2013

TRUCK TILTER & FUEL HANDLING SYSTEM ADVANCE AGRO
(2011-2013)
Capacity: 250 TONS/HOUR
Cost: 49 MILLION THB
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION
WET CAKE DILUTION PLANT FOR ETHANOL PROCESS DOUBLE A
(2011-2012)
Capacity: 700 TONS/DAY
Cost: 26 MILLION THB
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION
BELT CONVEYOR AND SCREW FEEDER BUA SIMMAI
(2010-2011)
Capacity: 300 TONS/DAY
Cost: 6 MILLION THB
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION
WOOD CHIP LOADING SYSTEM AAWTHAI
(2011)
Capacity: 600 TONS/HOUR
Cost: 60 MILLION THB
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION

2006-2008

BOTTOM ASH SYSTEM ADVANCE AGRO
(2008)
Capacity: N/A
Cost: 1 MILLION THB
Description
  • DESIGN+MODIFY
  • MANUFACTURING
  • INSTALLATION
WOOD CHIP CONVEYOR SYSTEM ADVANCE AGRO
(2008)
Capacity: 300 TONS/DAY
Cost: 8 MILLION THB
Description
  • DESIGN+MODIFY
  • FACTORY EXPANSIONS
TRUCK TILTER PROJECT ADVANCE AGRO
(2008)
Capacity: 60 TONS
Length: 15 METER
Cost: 5.8 MILLION THB
Description
  • DESIGN
  • MANUFACTURING
  • INSTALLATION
BELT CONVEYOR SYSTEM CHEME MAN
(2007)
Capacity: N/A
Cost: 5 MILLION THB
Description
  • DESIGN AND MANUFACTURE BUCKET ELEVETOR AND SILO WITH BELT CONVEYOR
CONVEYOR SYSTEM AND PALLETIZING MACHINES THAI GLASS INDUSTRIES
(2006)
Capacity: 2X500 BPM MAX
Cost: 11 MILLION THB
Description
  • TURN KEY;DESIGN AND INSTALL CONVEYOR SYSTEM AND PALLETIZING MACHINES
CONVEYOR SYSTEM AND MACHINES THAI PURE DRINK
(2006)
Capacity: 300 BPM MAX
Cost: 9 MILLION THB
Description
  • TURN KEY;DESIGN AND INSTALL CONVEYOR SYSTEM. FILLING MACHINE, LABELING MACHINE AND SHRINK SLEEVING MACHINR
CONVEYOR SYSTEM AND MACHINES MUANG MAI GUTHIRE
(2006)
Capacity: BOP
Cost: 5 MILLION THB
Description
  • TURN KEY; BOP OF HEATING-CHILLING SYSTEM PIPING, ACTIVATOR, MIXING PROCESS, RECONDITION BOILER AND CHILLING SYSTEM